'The Scope of Work relates to the excavation, dredging, and stockpiling works for Shurayrah Island, identified on Borrow pit and lagoon dredging sketch, and Shurayrah Earthwork filling area and Perimeter:
1. Shurayrah Island dredging
• Southern access channel and marina basin to design depths
• Southern lagoon to full depth, reducing the existing main lagoon section to design levels and opening the northern lagoon channel
• All internal channels to be reduced to design level
• Swimming channels to design depths
• North borrow area to a maximum depth of -5.0 m below seabed level
• Bathymetric surveys
• Geotechnical investigation
• Environmental monitoring
2. Shurayrah Island stockpiling
• Island topsoil removal, including vegetation clearance and screening of beach sand only
• Removal of mangroves
• Construction of primary bund
• Stockpiling of dredged material arising from dredging, land excavation and borrow area
• Treatment including isolation of fines from the dredged material if deemed unsuitable through daily testing
The island access will be from main land jetty to Shurayrah Jetty for land equipment mobilization to site.