The works under this Engineering, Procurement, Delivery, Installation, Testing and Commissioning Contract DS 233/1, consist of the following key elements:

Design and Construction of Terminal Pump Station (Civil, Mechanical, Electrical, Instrumentation and Control works) with dimensions 150mX175m (Foundation level -62.5m), Overflow Structure with Shoreline Outfall, Sea outfall (3 X 500 m HDPE pipes, 2,000 mm dia), hydraulic actuated penstocks and valves, HVAC, power supply distribution network, power transformers and switchgears, as well as all associated buildings, inclusive of Mechanical, Electrical, Instrumentation and Control works and external works.


 

 

.

Construction From: 11/2017
Construction To: 06/2020
Contract Amount (IN "000" US$): 272,000
Archirodon Portion: 100%
Owner: Dubai Municipality, Drainage and Irrigation Department
ID: 09053