Project Description

The project includes the construction of General Cargo Berth 340m length with 12m depth. In addition to this the project will include utilities to support its operation.

 

The scope of work includes the following :

-  Construction of RC Diaphragm walls (front, middle and rear)
-  Piling works for the connection between the main new quay wall and existing quay 8 and 9
-  Concrete works for quay wall and diaphragm walls
-  Fendering and mooring systems
-  Dredging works in front of new quay wall and disposal of dredged material to offshore area.
-  Apron pavement with precast concrete slabs.
-  Construction of Electrical Room, including MV system, Lighting and Fire fighting works.

Construction From: 06/2012
Construction To: 12/2013
Contract Amount (IN "000" US$): 15,006
Archirodon Portion: 100%
Owner: Damietta Port Authority
ID: 09014