The project included design, procurement, construction installation, hookup and mechanically complete with the Marine Facilities for the Urea & Ammonia Project.

The main items of work comprised :
  • Steel piled jetty including trestle, roadway, conveyor and pipe rack
  • A single berth jetty head comprising of loading platform, mooring dolphins, breasting fenders and catwalk.
  • Ammonia loading arm, Urea ship Loader, Jetty control building and associated utilities
  • Dredging of turning and maneuvering basin to the required depth.
  • Onshore Part of the trestle from the shore line to the battery limit at the DPA Fence
  • Sea outfall from onshore Plant to offshore

 

Construction From: 09/2007
Construction To: 10/2009
Contract Amount (IN "000" US$): 57,870
Archirodon Portion: 94% (Our portion: 54,426)
Owner: EAGRIUM ( A Joint Venture between Agrium Inc. and the Egyptian Petrochemical Holding Company (ECHEM)