The project includes EPC offshore works comprising 8x4m dia. X 3Km long GRP Discharge pipes with end diffusers, an intake channel comprising of a dredged channel and 2 rock breakwaters 1.4 km long, a seawater intake pumphouse 105m x 75m and the discharge chamber to the pipes (40x20m). EPC for offshore consisting of the ground improvement and backfill across the site of RO and MSF plants. The civil and building works include construction of RO building, RO switchgear building, waste water treatment, chemical dosing building, dissolve air floatation and 2 nos. dual media filters.

Construction From: 08/2010
Construction To: 01/2015
Contract Amount (IN "000" US$): 1,764,738
Archirodon Portion: 18% (our portion: 316,392)
Owner: Saline Water Conversion Corporation (SWCC)