Project Description
The project included the construction of the new breakwater, the Container Berths 5 & 6 with the corresponding Container Yard and associated buildings and services and the dredging of the new approach channel and port turning basin.
The main items of work comprised :

A. Construction of Breakwater, Dredging and Reclamation:
 - Dredging of the harbour basin and turning circle to -18 m CD level and the approach channel and entrance to -18.5 m CD.
 - Construction of the new breakwater (about 2850 m long) – comprising rock core, rock armour, accropodes and concrete crest wall.
 - Dismantling a portion of the existing breakwater. iv) Construction of bund between the new and the existing breakwater and reclaiming the enclosed area with dredged material/quarry run.
B. Construction of Container Berths and Associated Works:
- Civil works for construction of a 969 m long new quay structure for Container terminal (Berths 5&6) in Salalah Port, in continuation of the existing Container Berths Nos 1 to 4.
- Development of 345 m wide additional container yard on the upland areas of Berths Nos 5 & 6 including construction of supporting structures / systems for containers and yard equipment, roads, pavements, electro-mechanical services and communication.
- Miscellaneous marine works, provision of marine furniture. iv) Utility buildings and services

 

 

 

Construction From: 07/2005
Construction To: 03/2008
Contract Amount (IN "000" US$): 1,816,369
Archirodon Portion: 130,845 (50%)
Owner: Ministry of Transport and Communications Directorate General of Ports & Maritime Affairs