Project Description

The turnkey project included design, construction/manufacturing, testing and commissioning of the main work.

The main items of work comprised :
  • Civil, Structural & Building Works: including site development, foundations for equipment and structures, construction of seawater chamber, pumphouse and overflow pits, reconstruction of stacks, construction of roads, pavings and fencing, water supply, storm water and sewerage systems etc.
  • Electrical, Mechanical and Instrumentation Works: including Flue Gas Desulphurization Plant and associated equipment, electrostatic precipitator, cranes and lifts, electrical plant, air conditioning, fire fighting and telephone systems, water transfer system, compressed air station and instrumentation and control facilities etc.
Construction From: 11/2004
Construction To: 11/2009
Contract Amount (IN "000" US$): 80,727
Archirodon Portion: 100%
Owner: Saline Water Conversion Corporation (SWCC)
ID: 11045