Project Description The project included design, furnishing and construction of the offshore cooling water facilities and all services associated with these facilities for the Sidi Krir Units 3 & 4 Power Project.
The main items of work comprised :
- Two offshore cooling water intake structures
- Two offshore cooling water discharge diffusers
- Installation of two intake pipes from the two offshore intake structures to onshore circulating water pumps house interface location.
- Installation of two discharge pipes from the offshore discharge diffusers to the onshore interface location.
- Dolphins and warning signs
- Chlorine piping system
- Precast concrete block rip-rap protection
Construction From: 07/1999
Construction To: 02/2001
Contract Amount (IN "000" US$): 20,385
Archirodon Portion: 100%
Owner: Intergen Sidi Krir Generating Co. Egypt Main Contractor : Bechtel International Inc. Gaithersburg
ID: 01073