Project Description

The project included design and construction of additional Material Offloading Facilities (MOF) in Ras Laffan Port. The major items of work included 860m long quay wall on a prepared seabed with precast reinforced concrete blocks and insitu reinforced concrete capping beams on top. Rockfill and suitable material backfill behind the quaywall and scour protection at the toe of quaywall.

Construction From: 03/2006
Construction To: 08/2007
Contract Amount (IN "000" US$): 32,300
Archirodon Portion: 100%
Owner: Qatar Shell GTL Ltd.
ID: 01057

Testimonials