Project Description

The project incuded engineering, procurement and construction of the topsides facilities to the multi products berth.

The main items of work comprised :
  • Supply and installation of mech electrical topsides works to an existing berth including metering skids and loading arms.
  • Construction of ancillary administration building, fire station, electrical substation and renovation works.
  • Associated external access roads and infrastructure.
  • Removal of existing 24" dia. Submarine oil pipeline.
  • Construction of 1 no. Mooring dolphin involving precast blocks and in situ concrete.
  • Dredging 90,000 m3.
Construction From: 07/2002
Construction To: 08/2005
Contract Amount (IN "000" US$): 29,977
Archirodon Portion: 100%
Owner: Qatar Petroleum
ID: 01022