Project Description The project includes Marine, Civil, Mechanical and Electrical works for Phase 1 of the King Faisal Naval Base.
The main items of work comprise :
- Construction of Piers and Wharves to serve the base with a total length of approx. 3.6km with all associated marine furniture.
- Dredging works for widening and deepening the approach channel, turning basin and berths.
- MEI systems for potable water, fire fighting, sanitary, compressed air, diesel, lighting, telecommunications, and LV including all associated buildings, sheds and pumping stations.
Construction From: 08/2010
Construction To: 05/2017
Contract Amount (IN "000" US$): 199,034
Archirodon Portion: 100%
Owner: Commandership of Royal Naval Forces. Naval Forces Supply and Support Division